Clark County, Nevada Court
The plaintiff (Alimak) alleges that in October 2007 it entered into a sales agreement with the defendant (Republic Tower) whereby the defendant purchased six (6) construction hoists valued at $4,067,910. On December 5, 2008 the plaintiff informed via letter the defendant that it was in default and owed $2,688,694.89. At the date of the complaint filing, the defendant had failed to either “cure the default or surrender the Construction Hoists” to the plaintiff. Republic Tower & Hoist denied allegations. A settlement was reached in April 2009.
| Case No. |
08A578256 |
| Case Type: |
Breach of Contract |
| Date Filed: |
12/19/2008 |
| Location: |
Department 24 |
| Conversion Case Number: |
A578256 |
Click HERE to access the docket sheet.
Download Key Documents in the Case
|