Alimak Hek, Inc. et al v.
Republic Tower & Hoist, LLC


Clark County, Nevada Court

The plaintiff (Alimak) alleges that in October 2007 it entered into a sales agreement with the defendant (Republic Tower) whereby the defendant purchased six (6) construction hoists valued at $4,067,910. On December 5, 2008 the plaintiff informed via letter the defendant that it was in default and owed $2,688,694.89. At the date of the complaint filing, the defendant had failed to either “cure the default or surrender the Construction Hoists” to the plaintiff. Republic Tower & Hoist denied allegations. A settlement was reached in April 2009.

Case No. 08A578256
Case Type: Breach of Contract
Date Filed: 12/19/2008
Location: Department 24
Conversion Case Number: A578256

Click HERE to access the docket sheet.

Download Key Documents in the Case

1. Affidavit from Alimak CFO
12/19/2008
2. Exhibits to Affidavit
12/19/2008
3. Ex Parte Application for Order to Show Cause Why Collateral Should not be Taken from the Defendants and Delivered to Plaintiffs
12/19/2008
4. Plaintiff’s Reply Brief
01/27/2009
5. Order Granting Writ of Possession
03/04/2009
6. Dismissal with Prejudice
04/13/2009